Short answer
Before you hire a machine, settle four things. Ask whether the rate includes the operator and the fuel. Ask what delivery costs and when the hire period starts. Ask for the operator's certificate and the machine's latest test record. Find out who pays if the machine is damaged or stolen on your site.
1. What the rate includes
Ask whether the rate includes an operator, diesel or both. The words wet and dry are used loosely. See Wet hire or dry hire.
2. Delivery and the hire period
- Ask for the delivery and collection cost. One broker lists lowbed transport at R60 to R100 a kilometre.
- Ask when the clock starts. Under the Contractors Plant Hire Association's standard terms it starts when the machine leaves the owner's depot.
- Ask what happens when it rains. Under those terms you still pay when the machine is idle because of bad weather.
3. The papers
- The operator. On a construction site the operator must be certified competent and hold proof of competency. Lifting machine operators need a certificate of training.
- The machine. Cranes, forklifts and other lifting machines must be examined and tested at least every 12 months. If you lease one, you must keep the latest record on site.
4. Damage, theft and insurance
Under the association's standard terms the risk of loss or damage passes to the hirer when the hire starts. See Who pays if hired plant is damaged?
Questions people ask
What do I need to hire a TLB?
You need the site address, a description of the job and the dates. Ask whether the rate includes the operator and diesel, what delivery costs and what the minimum hire is. If you supply the operator, that person must be certified competent for the machine.
Can I hire a machine without an operator?
Yes, many companies offer the machine alone. On a construction site the person who drives it must be trained, certified competent and authorised in writing. If you have nobody like that, hire the machine with the company's operator.
Who checks that a hired crane or forklift is safe?
The owner must have it examined and tested by a registered lifting machinery inspector at intervals of no more than 12 months. As the user of a leased lifting machine you must keep the latest record on site, so ask for a copy with the machine.